West Main Place Drainage Project
Project Scope:
Improvements include installing approximately 500 ft. of new storm sewer with additional inlets as necessary to capture the flow in the streets. A sidewalk will be added along the north side of West Main Place for two reasons; to provide a barrier to keep the runoff in the roadway and out of the drive thru and secondly; connect the sidewalk on South Inglewood to W Main Street. West Main Place will be overlaid after the proposed work is complete.
***The Project began Monday, March 21, 2022. The project is expected to be substantially finished within 120 calendar days.***